中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
西北分公司多晶硅项目地管施工赢得甲方好评
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:27:48
西北分公司多晶硅项目地管施工目前进入紧张的攻坚阶段,全体参战人员正以饱满的工作热情加班加点奋战在施工一线,向“6·10全场地管安装完成”节点冲刺。
在时间节点日益临近的关键时刻,由于所订400余米DN2000地管材料图纸版次更新与终版图纸不符,自3月份地管施工开展以来,图纸、材料一直是制约施工进度的主要原因,如果重新再订货,不仅给甲方带来了一定的经济损失同时也使现场施工无法进行,而新增400米DN1400地管材料缺口能否到位情况直接影响工程进展,严重将造成窝工现象。在进退两难的关键时刻,我们年轻的技术员们想甲方所想急甲方所急,认真研究新版图纸并深入考察现场,根据现场实际情况提出了采用材料代用,积极联系设计和监理单位,很快征得一致同意,用已到货DN2000管子代用DN1400管子,到货管子全部充分利用,为甲方挽回高达70万元的损失,赢得甲方的表扬和感激。甲方管理人员激动地说:十一化建职工遇事沉着稳定、主动扎实的工作作风是施工单位中的楷模,与十一化建合作很满意也很愉快。在得到业主高度赞赏同时,也满足了现场需要,使我方施工进度得到保证。