中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
独山子乙烯裂解项目管道吹扫完成 保温紧张进行
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:27:51
5月15日下午7点,随着42区蒸汽阀门的缓缓关闭,引吭高歌40天的管道吹扫声音慢慢停止,至此独山子乙烯裂解B标段所有工艺管道吹扫打靶胜利完成,将进入试车前最后一道工序气密试验。
管道吹扫是检验管道清洁度的最终验收,需要业主一一确认。乙烯裂解装置共有工艺管道74公里,按流程分为30多个系统吹扫,除小部分管道用水冲洗外,其它的都采用压缩空气和蒸汽吹扫。项目部成立吹扫队,精心组织了15个作业组,并对参与人员进行安全和吹扫技术交底,进行详细的分工。两顿饭吃在现场,分两班24小时不停施工。在几家施工单位中我单位吹扫进度最快,受到业主表扬。
与此同时,管道保温和现场吹扫同步进行,项目部组织200多保温人员进驻现场。截至目前,保温工作完成总量70%,22区、27区保温已完成,5月底整个装置保温全部完成胜利在望。