中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神华包头工程指挥部气化装置开始单机试车吹扫试压
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:30:19
神华包头煤制烯烃项目气化装置自5月12日大干120天以来,到8月26日,由六公司负责施工的气化一区4台预热水泵率先拉开了单机试车的序幕。气化装置业已进入吹扫试车阶段,成为神华包头煤制烯烃项目第一个开始进行吹扫的装置,得到了业主的高度好评。
8月26日上午9时,总包、监理和业主全部到齐,随着业主代表的一声令下,操作人员按下启动按钮,4台电机相继启动运转,唱起了欢快的歌,在场的人员都露出了开心的笑容。经过几小时的运转,各种技术参数都达到了设计要求,一切正常,单机试车一次成功。
8月29日下午,蒸汽按预定时间进入了气化装置区,吹扫工作正式展开。8月30日,预热水系统、新鲜水系统、激冷水系统相继吹扫完毕。8月31日,燃料气系统、压缩空气系统也吹扫结束。至此,几个主要系统都完成了吹扫任务,开始投入试运转,为9月1日气化炉正式点火烘炉奠定了良好基础。