中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
内蒙古神舟硅业一期1500吨/年多晶硅机械竣工
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:49:12
12月8日,中国航天内蒙古神舟硅业有限公司与总包商中国成达公司在神舟硅业一期1500吨/年多晶硅项目机械竣工证书上签字,这标志着我公司有史以来承建的光伏产业项目中规模较大、装置最全的多晶硅工程完全交工。
神舟硅业一期项目建设中我公司承建了液氯、三氯氢硅合成、氯化氢合成、精馏提纯、还原、CDI1、CDI2、CDI3、冷冻、成品检测等所有主要装置。由于国内多晶硅技术不成熟、设计问题及工艺的特殊性,经历了超短线出硅、短线出硅和全流程基本贯通以及技术改造等阶段,同时施工过程发生设计变更单近1000份和工程技术联系单600多份,参战人员克服了材料、设计、进度和安全等重重困难,全面完成任务,为公司在光伏产业施工方面积累了丰富的经验。