中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
巴基斯坦项目部150MVA主变吊装完毕
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:27:07
4月11日,经过两昼夜的奔波,电仪一行6人到达巴基斯坦安德鲁施工现场。同志们不辞辛劳,经过严格安全培训后便迅速投入到现场施工中。
经了解,两台150MVA主变已在到达施工现场的路上,随时可能到达施工现场。经过对图纸和资料的熟悉,了解到此变压器的器身非常庞大,在无油的情况下变压器主体的重量达到了110T。为了减少工程成本和加快施工进度,工程师和班长立即进行现场勘察并和吊装人员进行详细商谈,最后决定将变压器本体一次吊装入位。工程师和班长分别对施工图纸进行仔细的研读,讨论并确定出主变中心线和主变基础中心线的具体数据,并在主变主体和主变基础上标示出具体的位置,以利于起重工师傅们顺利吊装。为了此次吊装召开了电仪人员动员会,以保证工作的顺利进行。
4月14日下午,变压器主体及附件到达施工现场,工程师再一次的叮嘱,这是我们到达巴基斯坦工地做的第一件工作,一定要做到精准,尽量使误差最小,使投资者和总承包商满意并向五公司交出第一份优秀的试卷。在班长的带领下,电仪人员配合起重对150MVA主变主体的一次吊装就位工作。由于准备工作充分,变压器主体的吊装工作进行的非常顺利。业主在对第一台变压器的就位尺寸测量后,伸出了大拇指连说OK,very good!当两台变压器主体吊装完毕后,我们才发现在40°的温度下已是满身的汗水,工作服已经被汗水湿透。虽然这里炎热的天气是我们所面临的最大问题,但是并不能阻碍我们电仪人的施工热情,在今后的施工中我们将交上更多优异的试卷。