中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神华包头煤制烯烃项目设备吊装显神威
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:27:13
由七公司承建的神华包头煤制烯烃项目净化装置,其大部分设备都安装在泵房两侧钢结构的框架之间和框架中,空间狭小,设备吊装难度大。
2月中旬,七公司参战职工在党委书记白涛、经理助理高建国的带领下,陆续调遣到冰天雪地的塞外包头,先期到达的安装十一队经过短期的进场培训后,便投入到前期的施工准备中,于3月18日吊装第一台设备,并拉开了设备吊装的序幕。
进入4月,为使到货设备及时卸车,安装十一队起重班加班加点的全天守候在现场,他们常常错过了中午吃饭时间,等他们卸车完,吊车收了杆,送到现场的加班饭也已经凉了。为了不影响设备吊装,质检科及时组织现场有关人员进行设备基础的自检和复检工作,设备卸车后及时吊装就位,缩短了设备滞留时间,提高了吊车使用率,保证了施工进度。设备就位离不开钳工班师傅们的辛苦劳动,设备基础交付后,他们立即在基础上打麻面,安放垫铁,设备就位后他们又进行设备找正,安装数据准确到位,得到监理、业主的好评。
截至目前,神华包头煤制烯烃项目净化装置吊装设备54台,其中20吨以上的设备38台,平均一天吊装一台设备,速度之快,在整个神华包头煤制烯烃项目上首屈一指。