中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
江阴工地打好设备安装就位第一仗
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:27:24
江阴三房巷华怡聚合工程从3月10日开工至4月20日短短的40天共完成了310台设备的就位工作,其中有260台已具备配管条件。
江阴三房巷华怡聚合CP10、CP11工程甲方对工期要求的非常紧,要求必须在七月份达到中交条件, CP10、CP11共有设备478台,其中利旧设备70台。这70台设备是从老厂拆下再利用的,为现场施工又增加了难度。项目经理郭卫林与甲方协调了一辆叉车,一辆板车以便使用,并与技术员陆新峰经常去现场进行巡视。在起重班长周文海的带领下,分为两组作业,只要甲方有设备进入现场,他们就在第一时间进行设备的运送工作。钳工由李富贵、李家来两位师傅分为两组进行现场作业,他们总是第一时间对现场就位的设备进行找正工作,一会测水平、一会找中心、一会量标高,如果不够高还要加垫铁。
正由于现场大家的团结协作,努力工作,才能在如此短的时间内完成这么多的工作量,平均每天达到就位设备近8台,找正设备近7台。创造了一个新的记录,也为7月份的顺利中交打下了坚实的基础。