中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
江阴项目部管道安装全面展开
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:28:02
江阴三房巷华怡聚合工程从4月初开始到5月中旬短短的一个半月时间里,共完成了工艺管道预制8333米,安装5808米,预制打因口27980个,安装打因口18163个,管道安装全面展开。
华怡聚合(CP10、CP11)工程甲方要求必须在7月份达到中交条件。由于3月份才进点开工,设备安装还不到位。项目经理郭卫林作出决定,对已就位达到配管条件的管道进行预制安装,对达不到条件的就先进行管道的预制工作,等货达到条件后再进行安装工作。技术组长也立即组织相关技术人员把能干的图纸先抽检出来分发到各施工队。
4月初人员陆续来到现场,由于先期准备工作已经做好,所以班组一进入现场就可以全面进行管道的施工工作,管道的顺利制安,为今后管道施工能够按时交工创造了条件,也为7月份的中交打下了基础。