中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
巴基斯坦卡迪普电站项目部电厂双T板安装结束
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:29:02
巴基斯坦卡迪普电站维修车间和仓库的双T板于6月18日顺利安装结束。
巴基斯坦仅有两个厂家可以生产双T板,由于我们订货数量较少,构件尺寸超长(18米),距生产厂家很远(570公里),厂家一直对供应该批砼构件不感兴趣,经项目经理汤总决策,经过半年多的谈判、磋商,终于从本月15日开始进入运输、安装阶段,经过4天的紧张施工,截至18日下午,最后一块双T板安装顺利结束。
此建筑双T板的顺利安装,为项目解决临时设施的紧张局面起到很大的缓解作用,该厂房将作为电仪临时仓库首先投入使用。