中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
鄂尔多斯多晶硅项目部脱盐水室内设备顺利吊装就位
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:29:14
7月18日20点,西北分公司多晶硅项目部脱盐水室内机械过滤器1号、2号、3号顺利就位,这是多晶硅项目设备安装第一吊,标志着设备安装工作的全面展开。
脱盐水室内设备共有40余台,由于甲方设备采购问题导致设备延期到货,而框架已经浇筑封顶,且设备高度与屋顶高度相差很小,给设备安装工作带来了很大的难度。要先在屋顶上打吊装孔,用钢丝绳从孔中穿过,使用吊车与倒链配合将室外的设备放置到设备基础上。为了保证吊装工作顺利进行,项目施工经理张旭、项目总工徐好兵、安装队支部书记刘文标及其他管理人员针对室内吊装难度大的特点,进行现场实际测量探讨最佳的吊装方案,并与参与吊装人员做了详细的安全技术交底,将一切吊装准备工作安排就绪。17:20随着起重班长邢乃增的一声清脆哨响,吊装工作正式开始,高温酷暑天气丝毫没有影响职工的工作激情,经过近3个小时的吊装及找正,3台机械过滤器准确的坐落在设备基础上。精益求精的技术要求和娴熟的吊装操作过程得到了业主的高度称赞。