中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
霍林河项目部空冷岛热态冲洗被树为典范
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:29:21
7月8日上午8时30分,霍煤试运指挥部会议室内,东北电科院调试赵总郑重宣布霍林河5#机组空冷岛热态冲洗工作结束,这个结果出乎所有专家的意料。整个热态冲洗仅进行了32小时,而通常空冷岛的热态冲洗往往要进行半个月以上。
从冲洗水取样数据来看,在冲洗后2小时取的第一次样就已接近合格标准,最后6个样的洁净度已经接近精处理水的标准,均高于热态冲洗要求标准10倍以上,完全可以判定为合格。在场的调试专家都称:他们调试过很多套机组,这套机组空冷岛的热态冲洗进行时间最短,效果却最好,整套机组少运行了10多天,直接节省的运行费用就达百万元之多。热态冲洗是一道关键工序,意味着总工期提前了10多天。蒙东能源集团坑口电厂陈总要求我们将整个施工过程的洁净度控制进行总结汇报,作为一个典范在工程管理中进行推广。
这是霍林河项目部继去年排汽管道制作样板工程后,又一次被树为典范推广。