中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神华包头指挥部气化装置管道试压工作全面展开
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:29:43
进入7月中旬以来,神华包头煤制烯烃项目气化装置为了确保11?18中交目标的实现,指挥部提出了“以试压来推动管道安装”的战略,成立了试压试车领导小组,迅速展开了试压包编制工作,狠抓管道成型率和完善工作,与此同时,对条件成熟的管线率先展开试压,从而使试压工作全面展开。
六公司工程技术人员仔细盘查管道施工量,围绕设备和系统认真编制试压包方案,排出试压网络图,督促条件基本成熟的管线尽快完善成型,具备试压条件,提早进行试压工作。安装二队钳工班、起重班等作业人员严格按照项目部的部署安排,积极做好设备及管道的试压准备工作,想方设法踏点试压。截至发稿时已完成试压包21个,完成总量的7%左右,取得了初步战果,为8月份试压工作的全面展开奠定了良好基础。