中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神华包头煤制烯烃项目进入中交倒计时
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:30:22
公司承建的神华包头煤制烯烃项目气化装置、净化装置距11?18中交只有80多天时间了,工程建设如火如荼,大干高潮接连不断。
一走进气化现场,醒目的倒计时牌最引人注目。大干120天的序幕还没有落下,指挥部就下达了新的指令:9月1日点火烘炉目标必须确保。整个施工现场热火朝天,大干高潮迭起,施工进度突飞猛进,工程形象日新月异。
气化项目中午送饭到现场,晚上延到8点。净化项目施工已进入工艺管线试压阶段,8月12日,成立试压领导小组。19日上午,第一个试压包送出报审一次检验合格,下午1点,开始管线上水试压,进过3个小时的上水、保压过程,下午4点管线试压成功。
全体施工人员正在全力以赴的奋力拼搏,确保11月18日实现工程中交。