中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
乌石化项目部大干60天见成效
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:30:29
中间罐区项目是乌石化项目部2009年的主营业务工程,由于受到场地的影响,至到8月1日才正式开工,本来有9个月施工工期的项目,现在必须两个月完工,在这种情况下项目部领导果断采取流水施工的办法,让土建队集中精力干部分基础,先交付安装使用,再干其它划分好的基础,这样大大提高了施工进度,同时也避免了工人们工作的两极分化。就这样短短一个月时间内,5000m31台、3000m31台、2000m32台罐基础施工完成,2000m31台、1000m31台已开挖完毕;配电室基础施工完成,正在进行柱钢筋帮扎。并且5000m31台、3000m31台、2000m32台这4台罐底板及第一带板安装完成,罐顶正在安装。90吨的钢结构也预制完毕,等待进入现场安装。
当然这些成果和现场工人师傅们争分夺秒的奋力拼搏是分不开的。自8月2日掀起大干60天高潮以来,项目部施工高潮此起彼伏,相信在项目部的领导下,一定能按时完成中交,向业主交上满意的答卷。