中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
鹤壁项目部气化框架混凝土结构顺利封顶
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:30:16
由三公司承建的鹤壁60万吨甲醇项目气化主框架工程,经过土建一队全体员工的紧张施工,已于8月13日胜利顺利封顶,并于8月28日交付安装。
气化框架混凝土结构高为40米,南北方向为25.7米,东西方向为44.7米,共划分为5层,每层柱子共15个,柱截面为2米。总共完成钢筋量达到2800吨,混凝土量达到8300立方米。
在7月份施工的40米层的厚板,高为3.3米,迄今为止是国内气化框架最厚的板,施工难度大,技术含量高。由于雨季来临,如果施工滞后,势必影响全体工程的进度,高峰期每天晚上加班到12点。在施工厚板前及时地成立了领导小组,小组成员每天呆在现场指导技术工作,每完成一部分工作量均做到全面检查,取得合格数据后才可以进行下部工作程序。由于制度落实、工作到位、奖惩分明,调动了大家的积极性,促进了企业的全面发展,有效的保证了工期,得到了业主的一致认可。