中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神舟硅业一期多晶硅项目所有扫尾工作进入尾声
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:30:49
截至9月10日,神舟硅业一期1500吨/年多晶硅工程所有参战单位遗留的830项不同大小的尾工,在七公司安装五队为期20天的不分昼夜的扫尾工作中,逐一得到有效地解决。
从CDI、CDⅡ、CDⅢ、精馏提纯到氯化氢合成;从液氯车间到大小冷冻厂房;从锅炉岛、成品车间到高危险区域还原车间,每一处到留下了十一化建人忙碌的身影。为了配合业主顺利开车,安装五队在队长陈汴生的带领下,在整个一期工程,24小时全天候准备着为业主解决工程尾项和开车过程中所遇到的问题,业主和监理都形象地称呼安装五队的同志们为“现场110”。目前,神舟硅业一期830项大小尾工,除设计缺陷和工艺缺陷所产生的尾项外,所有均已顺利完成,圆满完成公司和项目部领导交付的任务。