中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
神华包头煤制烯烃指挥部夯实基础管理
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:46:52
10月4日,神华包头煤制烯烃指挥部召开调度大会,公司副总经理、指挥部指挥长韩长恩强调:全体参战人员一定要再接再厉,再努一把力,坚持最后的40天大干劲头,夯实基础管理,自加压力,确保项目11月18日按时中交,力争提前中交,为两年来在内蒙包头的努力奋斗画上圆满的句号,为公司再创佳绩,创造良好的信誉,与会的各公司经理都表示,再努一把力,打好试压收尾这一仗,干好工程,服好务,赢得社会信誉、政治信誉的双丰收。
神华包头煤制烯烃项目气化装置已经进入施工倒计时40天的关键时刻,122气化工段,123渣水工段管道、设备、钢结构等工程的安装工作已经基本结束,正在进行繁忙的试压扫尾;项目部参战的六分公司、中原分公司、内蒙分公司派出精兵强将进行管道、结构的“三查四定”等工作;钢结构、管道、设备全部尾工上墙,每天下午六点钟召开项目碰头会,在会上各单位说明前一天定下的尾工任务完成情况,没有完成的说明原因,再定目标,确保安装收尾工作的正点完成。