中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
鄂尔多斯多晶硅项目部管廊钢结构安装全面展开
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:47:05
10月24日上午9点,西北分公司多晶硅项目管廊钢结构吊装顺利展开,为下一步工艺配管、电缆桥架及电缆敷设施工奠定了基础。
管廊全长1500米,钢结构制作安装1600多吨,后续还有工艺管线约30000米、电缆桁架6000米要在冬季施工完成。但是由于钢结构图纸、材料到货较晚,直到10月中旬钢结构预制才具备大面积展开条件,施工有效工期被大幅压缩,严重影响后续工作。
10月中下旬后内蒙气温夜间已经降到零度左右,面对工期、技术、天气等诸多不利条件的影响,项目部积极应对,及时调整作息时间,职工中午不休息、加班加点奋战在施工一线,整个现场一片忙而有序的施工景象。管廊框架制作场地狭窄、也给预制工作带来一定难度,项目部要求参战班组加大钢结构预制深度,尽可能把具备条件的部件组装焊接完成,大大节约吊装时间和高空作业安装时间,提高了安装进度,保证了施工安全。经过全体职工的共同努力,管廊框架安装现已全面展开。