中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
宁煤工程黑水装置三台滤液收集罐安装就位
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:48:11
11月15日,大雪后的神华宁煤黑水装置压滤厂房一隅,八公司安一队起重班的6位师傅,正在齐脚深的雪地里忙碌着,个个干得头上直冒热气,喧闹的场面与冰冷的天气形成了鲜明对比。
据现场施工负责人、安一队副队长孔文轲介绍,今天需完成自制设备滤液收集罐的安装任务,滤液收集罐共3台,分别重约5吨,高4米,直径3.5米,安装位置位于压滤厂房一楼。设备虽不重,安装标高低,但厂房内路面坑洼不平,各种基础又裸露于地面,给设备托运造成了极大阻碍。有困难要千方百计去克服,迎难而上正是化建人的本色。
经过反复磋商,决定在厂房设备入口对面设置一台卷扬机牵引设备,并将设备放在固定的道木垛上,下面垫以滚杠增加设备高度,有效避开了各种障碍物,使设备能顺利地被牵引至基础旁。
过程虽不复杂,但具体操作起来全靠人工手抬肩扛,劳动强度颇大。起重班几位师傅共同努力、相互协作,一切准备工作就绪后,随着老师傅马岐凤的一声哨响,卷扬机缓缓转动牵引着设备一点点前进,其他人员则密切注视设备运行状况,及时挪动滚杠、搬运道木,60米的两次搬运路程通过在场人员的努力,30分钟即牵引到位并吊装成功。紧接着,一样的程序一样的步骤重演两遍,仅仅半天时间,3台滤液收集罐全部安装就位,比原计划缩短一倍时间。至此,黑水压滤厂房最关键的3台设备安装结束,八公司朝着年底黑水装置设备机械竣工的目标又迈进了一步。