中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
鄂尔多斯多晶硅项目部最后一台设备顺利就位
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:56:42
7月13日,西北分公司多晶硅项目部圆满完成了设备吊装的收官之作,最后一台设备氢化氯硅烷冷却器顺利吊装就位。
氢化氯硅烷冷却器长8.25米、高1.8米,净重12000kg,位于尾气回收框架二层平台中部,因5月初到货后检修不合格返厂处理,迟来两个多月,其他设备、工艺管道和电气仪表等已全部安装完毕,如果走近路吊装需要拆除一台换热器和工艺管线,且工艺管线均已完成试压工作。分公司用吊车把冷却器送至二层平台外侧,然后用倒链接入框架平台上,用2台10吨倒链作为起吊主要吊具,再用2台5吨倒链作为牵引和辅助吊具进行吊装。在全体吊装人员的共同努力下,7月14日上午,冷却器终于稳稳地安装在基础上,比原计划提前一天半完成吊装,得到业主的高度赞扬。
我公司承担的多晶硅项目16个单位工程,共计259台设备已全部安装完成,向工程早日建成投产又迈进了一步。