中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
蒙维科技项目部第一吊
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:59:10
10月1日,一清早,在举国同庆的伟大历史时刻,为保施工工期项目部全体员工冒着小雨坚持奋战在施工一线,组织人员机械立起了蒙维项目部全场外管廊的第一根钢柱,这是我公司蒙维科技项目经理部的第一吊,标志着我公司在蒙维科技项目部的吊装、安装工作拉开了序幕。
全场外管廊总长1300余米,近300座独立基础,目前已完成80%基础施工,为响应业主要求,钢结构施工更是迅速,在保证质量的前提下,短短两星期完成600余吨的制作量,整个施工过程得到业主认可和好评,表示十一化建是值得信赖和依靠的单位。现场目前处于多雨季节,且此项目地处内蒙地区多风口位置,是冬季最冷地区之一,近几天气温最低已达零下5度,良好的施工时间即将过去,我们要抓住良好的时机,利用一切可以利用的条件,争取在有利的时间里完成更大的工程量。为下一年工作开展创造有利空间和良好条件,交上一份让业主满意的答卷。