中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
独山子焚烧炉项目施工如火如荼
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:59:42
独山子焚烧炉项目200km的电缆铺设工作在9月22日已经开始,目前已经铺设35km,计划在10月下旬完成全部的电缆铺设。安装作业目前正在紧张进行加药间2台德国进口设备的安装以及焚烧线的工艺配管工作。
焚烧炉项目是独山子千万吨炼油百万吨乙烯配套环保项目,在中油系统尚属首套,能否顺利建成关系到大发展项目的申报工作,为此备受独石化公司重视。此项目也是我公司首次承建的环保项目,因此从3月份进点开工以来,我们就做好了充分的准备工作。由于种种原因,使安装、仪电施工计划一拖再拖,随着天气的逐渐转凉,剩余的施工时间越来越少,为了抓住施工的黄金季节,按时、高质完成施工任务,项目部全体人员每天工作11个小时以上,两顿饭吃在现场,加班加点抢时间、赶进度。
Previous News:独山子顺丁橡胶4台聚合釜吊装就位