中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
新乡中新化工项目部乙二醇地下管网工程进展迅速
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 17:59:44
七公司承建的新乡永金化工乙二醇地下管网工程,8月30日开工至今已经完成地下管道敷设3000米,得到了开工组织迅速,工程施工迅速的良好赞誉。
该工程是新乡永金化工乙二醇项目的前期工程,地下管网全长5000米,其中地管的最大管径¢1820mm,属于超大管径,地下管网管道中心标高深埋于-5.4米及-3.2米,敷设地下管道,需开挖管槽上宽12.5米管、槽底宽6.4米、深6.31米的管沟,为防止滑坡等意外事故的发生,开工前期,项目部就对施工人员进行安全技术交底,在开挖管沟、打井降水施工中,都做到了安全管理层层把关。
目前,乙二醇地下管网施工进展迅速,已经完成工程量的60%,超大管径全部敷设下沟,后期试压工作正着手准备,为永金化工乙二醇项目部开辟了一个良好的开端。