中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
焦作聚氯乙烯工程进入单体试车阶段
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 18:02:19
由第八工程公司承建的焦作聚氯乙烯工程日前进入单体试车阶段。
为确保12月31日单体试车一次成功,八公司焦作工程项目部全体参战人员冒着严寒、加班加点、日夜奋战在施工现场,他们克服了天气寒冷,施工难度大、设备到货晚等诸多因素,想法设法排除了施工中遇到的重重困难,突破了技术上的种种难关,在确保安全和质量的前提下,按甲方的要求提前达到节点,得到了甲方的好评。
截止到12月19日下午,焦作聚氯乙烯工程的设备全部安装完毕,电缆基本敷设完毕,电气调试工作基本完成,设备均已具备单体试车的条件,为聚氯乙烯工程联动试车打下了良好的基础。
(八公司 焦铭莉)