中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
衡水离子膜烧碱工程一次投料成功
From:Our Website Author:Admin
Views:0
Published Time:2016年11月12日 18:09:22
衡水讯
5月17日夜,由中化制安公司衡水项目部承建的河北冀衡化学10万吨/年离子膜烧碱工程项目一次投料成功,顺利生产出合格产品。
该工程于2010年9月开工,因为是在老装置旁扩建必须保证原来生产的正常进行,安全要求严,现场施工要求规范高,无形中增加了很多施工难度。特别是在与老装置合并系统时,要求仪表、电气、设备工艺,都要达到生产状态,是不能出丝毫差错的,稍有失误就会前功尽弃。项目部全体员工克服施工设备、施工材料不到位,发货不齐全、焊接要求高、电解槽安装精度高、工艺复杂,时间紧,且工作量边干边增加等种种困难,于2011年5月18日顺利竣工,历时8个月
。(中化制安公司 尤冬梅)