中文
EN
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Company Honor
Country Gold Medal
Country Silver Medal
Excellent Project
Technology and Progression
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery projectt
Petro-Chemi. Project
Coal-Chemi. Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award Project
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
中文
EN
✕
Home Page
About Us
Company Profile
Director Speeches
Company Leadership
Organization
Development Strategy
Honor
Company Qualification
Company Credit
Company Honor
Luban Engineering Award
National Gold Medal
National Silver Medal
Hundred Classics
Technology Innovation and Progress
Star-rated Standardized Construction Site
Advantage
Design
Civil Engineering
Installation
Electrical Instrument
Project
refinery project
Petro-Chemi. Project
Coal Chemical Project
Chemical Project
Muni.&E Project
Electrical Work
Synthetic Project
Biol-Chemical Work
PC/EPC Project
Award-winning Projects Overview
Recruitment
Talent Strategy
Talent Training
Talent Team
Recruitment Information
Corporate Culture
Corporate Philosophy
Corporate Video
Cultural Activities
Safety Production Commitment
Contact Us
Major Business Management Matters
Wage Arrears Complaint
Contact Us
News Detail
Learn more about our company and its history.
越南金瓯化肥工程项目部再掀施工大干高潮
From:Our Website Author:Admin
Views:0
Published Time:2016年11月14日 09:12:14
越南金瓯讯
越南金瓯化肥项目胜利完成8.31机械竣工目标后,再次掀起施工大干高潮,项目部制定了详细的施工倒排计划、试车试压经济责任制、专业节点计划等,各项措施的有力推行,进一步调动了广大参战职工的积极性、能动性,各专业、各工种克服雨季施工的诸多困难全力拼抢,确保11.27出尿素的目标实现。
截至目前,管道施工已接近尾声;吹扫工作有条不紊地进行中;管道试压如火如荼已完成40个试压包,以试压促施工工作大见成效;辅助锅炉烘炉顺利结束,烟道风机带负荷试车圆满成功,即将开始煮炉工作;全厂近80台动设备单机试车在设备队和仪电队的共同努力下,具备条件的已经全部试车完毕,现正在进行复合试车;4台压缩机、4台高压泵、2台风机的油循环工作接近尾声,已有3台通过了验收;电气施工已完成95%的工作量,仪表主电缆120公里敷设结束,分支电缆正在紧张进行,现场仪表已完成70%,为下一步的联动试车、联校打下了基础。
项目部全体职工正以饱满的工作热情,克服多重困难,向11.27目标全力冲刺。
(记者 向东报道)