In the morning of May 12th, the director Hu Haiyin and his party of China National Chemical Engineering Corporation visited our company for investigation and research. In t...
At 11:00 on July 1, the symposium held in the Xinjiang Sino-Thai Toksun project meeting room, all the communist and the active applicants for CPCattended the meeting. The ...
In the afternoon of May 23nd, Our chairman Li Shiju, vice general manager Fan Changyun investigated the Toksun project. After looking over the project site, Mr. Li Shiju a...
At June 3 pm, the start-up heater of Indonesia PKG Project had a successful hoisting in position. This equipment with a weight of 165 ton, diameter 6.5m and height 16m, ...
The company Malaysia RAPID TR Project held ceremony meeting at site on July 1, 2017 for our party 96th Birthday. The meeting should has project party member 40 persons ...
Recently, the BUPC air separation plant cold box and storage tank installation construction project in Iran Assaluyehto be built by No.5 Construction Sub-Company, has been co...
At 6th June 5 pm, self-bulid mixing station in Zhongtai Toksun Chemical Project which built by Xinjiang branch company, after a month installation and debugging, production ...
At 5:30 pm of July 3rd, the Sino-Thai chemical Toksun high-performance resin project polymerization device recovery gas cabinet foundation began to be poured by the XinjiangC...
The temporary facilities of Zhongtai Chemical Toksun high performance resin industry and supporting infrastructure construction project which built by Xinjiang branch company is...
Shanghai COVESTRO TDI factory Shutdown form May 29th, After 3 weeks of intense work, in June 22nd, the device drove successfully and returned to normal production. During t...