The wallboard installation of two 10000m3 storage tanks in MPS station of Saudi
source:local site author:administrator create:2016-11-10 00:00:00
By scientific plan and exact organization of project management team, go through the hard work about three months, the installation of two 10000m3 storage tanks in MPS station of Saudi SWCC Project finally has significant development, all the wallboard had been assembled and welded, so as to make a good preparation for remaining roof of following storage tank.
MPS station is far away from project camp, with the bad hot weather of Aug. and Sep., especially in the afternoon, there are often wild wind and flying dust, but our management team and construction workers has worked in close coordination at the station with the hardworking spirit, got over all kinds of negative factor, planned as whole, prepared and arranged the work seriously, communicated with supervisor positively, the workers has been trained in safety and overall technical disclosure for ensuing the installation work smoothly such as baseboard, center pole, roof plate hoisting, wallboard assembling and welding and so on.
By report, following the construction of project home field is nearly completed, the civil work of main pump room, power room and so on in MPS station would be started. (Saudi Branch Lv Zhenbin)
Editer:FangYuan