Dalian Hengli petrochemical project conquered sandstorm in indomitable spirit
source:local site author:administrator create:2017-05-24 16:02:00
At 7 AM of May 19
th, all staff of Dalian Hengli petrochemical project constructed by company completed 2985 m³of concrete work by 21 hours of hard work.
The concrete pouring is the largest amount of sewage treatment equipment undertaken by the company, and it is also the largest amount of concrete pouring at the same time; the development units, supervision units, construction units, director of concrete mixing station were very serious to request the construction unit that: because the maximum amount of concrete pouring, hope ELECO to carry forward the spirit of construction, to ensure the quality of concrete construction.
According to the construction plan of project, put into 3 sets of concrete pump car,9 sets of concrete tanker, 12 workers for concrete vibrating pump, 27 persons for pouring concrete, 12 persons for plastering. At 10 am, our staffswere not afraid of sand and wind, still insist on construction work until the final process. Thedevelopment unit is moved to praise that: the constructors of ELECO are really invincible! (Photo and report by Zhang Wenliang)