Iran Project at Peak in Piping and Storage Tank Installation
source:local site author:administrator create:2017-06-01 16:10:00
Recently, the BUPC air separation plant cold box and storage tank installation construction project in Iran Assaluyehto be built by No.5 Construction Sub-Company, has been completed cold box main body of steel installation and equipment hoisting. The project department is committed to the installation of the pipe in the cold box and the construction of the storage tank.
It has been completed within the cold box on the upper and lower tower hoisting for 2, the total weight of 213t; heat exchanger 12, the total weight of 145t; subcooler for 2, the total weight of 17t; 388t total weight of the main steel structure of the cold box board;prefabrication and installation of aluminum pipe in cold boxhas been completed 8600 dyne, accounting for 41% of the total. The Project Department stressed that: the core of the project is the quality and safety, mainly concerned about the cleanliness of the cold box and welding quality, to be promptly corrected if found the security risks. Everyone is a security officer, everyone is a quality inspector, found the problem and corrected promptly.
Under the careful organization and arrangements of the project department leadership team, the construction progressis far beyond the expected plan within three months. Owner, supervision andgeneral contractorhas given high praise to our company.(Reporter: Yao Weiyuan)